Day 14 & 15 - Light sanding of primer & painting canoe

Day 13 - Paint priming canoe

Day 4 - Adding gunwales

Day 3 - Removing wire stitches, filling holes & fiber glassing joints

Day 2 - Stitching & Gluing Panels

Day 1 - Lofting, Cutting & Gluing Panels

14 Ft. Flat Bottom Canoe Building Project

Brian's 360 Detailing & Cleaning

916-752-2308


Day 5 & 6 - Sanding & fiber glassing gunwales

Day 9 & 10 - Light sanding & second coat of epoxy resin on exterior sides. Sanding & epoxy resin interior.

Day 8 - Trimming off excess fiber glass, and applying second coat of epoxy resin to bottom

Day 7 - Fiber glassing exterior

Day 11 - Light sanding, priming bottom of canoe

Day 12 - Light sanding of primer, painting bottom of canoe

Day 16 - Finishing touches